Commissioning & Handover

Testing & Commissioning (Cx)

CoreInfra insists that commissioning be engaged early, from the planning and design stage. Following an internationally authoritative Commissioning framework, our rigorous five-level verification ensures the data center reaches the highest availability and stability before going live.

L1–L5 Framework

The critical line that proves a data center "works"

From factory testing to full heat-load operation, five levels of verification prove every system before it carries live workloads.

L1

Planning

Factory Witness Test (FAT) — planning and testing of critical equipment at the factory.

L2

Site Inspection

Site Acceptance Inspection — equipment delivery handover and static installation checks.

L3

Pre-functional

Pre-functional Testing — single-equipment energization and basic functional run tests.

L4

Functional

Functional Performance Testing — cross-system interaction and interlock-protection logic verification.

L5

Integrated Load

Integrated System Testing — simulated full-load operation and failover drills.

Verification Technology

Professional verification techniques

Thermal Simulation

Using infrared thermal imaging and heat-load simulation equipment to measure and analyze airflow organization and cooling efficiency in the hall.

Power System Stability

Full-load blackout simulations for UPS, generators, and transfer switches (ATS/STS), ensuring seamless switchover under extreme conditions.

Operations Handover

Ensuring as-built drawings, test reports, and operating manuals are fully archived, and helping the O&M team complete site orientation.